Parkes Lions Park Playground Upgrades

  • Project typeGrant and Council Funded
  • Project value$850,000
  • Project scheduleCompleted
  • Contractor nameParkes Shire Council
DJI_0114.JPG

 The project involves the removal and construction of new play equipment and associated BBQ amenities. The Australian Government, through the Local Roads and Community Infrastructure Program, will contribute $415,000 to the $850,000 project. 

The new play space will include: 

  • 25m double sky rider (flying fox)
  • Multi-play skytower
  • Rock climbing block
  • Swing set with an inclusive seat
  • 2.3m wheelchair-accessible carousel
  • Three mini trampolines
  • A balance trail
  • A junior multi-play unit
  • A winding bike path
  • additional play equipment shade
  • new shelters
  • New barbeques

Project Updates

August 2023

  • Lions Park Playground Upgrades is now completed. 

July 2023

  • Finishing components of the park including:
    • Line marking path
    • final surface instillation

    Press left and right keys to move between slides.

    1. 1
    2. 2
    DJI_0131.JPG
    DJI_0114.JPG

July 2023

  • Play equipment installed
  • Rubber surface installed

Press left and right keys to move between slides.

  1. 1
  2. 2
IMG_5698.JPG
IMG_5704.JPG

June 2023

  • Sandstone block work completed 
  • Sandstone garden edging works completed
  • Shared Footpaths commenced and progressing
  • New shelter install commenced

Play equipment install schedule to commence 19 July

Press left and right keys to move between slides.

  1. 1
  2. 2
  3. 3
  4. 4
  5. 5
IMG_5529-min.jpg
IMG_5534-min.jpg
IMG_5535-min.jpg
IMG_5536-min.jpg
IMG_5538-min.jpg

May 2023

  • Base works for paths, rubber soft pour & synthetic turf
  • Sandstone block work for retainers & landscaping

Press left and right keys to move between slides.

  1. 1
  2. 2
  3. 3
  4. 4
  5. 5
IMG_5481.JPG
IMG_5482.JPG
IMG_5483.JPG
IMG_5484.JPG
IMG_5485.JPG

May 2023

  • All demolition been completed
  • Concrete slabs for shelters & BBQ's have been completed
  • New conduits for power and CCTV is installed
  • Sub surface drainage works are now complete
  • Earth works for footpath and play equipment is underway

Press left and right keys to move between slides.

  1. 1
  2. 2
  3. 3
  4. 4
  5. 5
IMG_2474.jpg
IMG_2475.jpg
IMG_2476.jpg
IMG_2477.jpg
IMG_5399.jpg

April 2023

Construction on the Lions Park play equipment upgrades has commenced. Removal of Play equipment and BBQ shelters is currently underway.

Press left and right keys to move between slides.

  1. 1
  2. 2
Lions-park-construction-2.jpg
Lions-part-construction-1.jpg

Location

9 Molong Road, Parkes 2870  View Map